CRAFT · 14 SEPTEMBER 2026 · 6 MIN

Everything that leaves the yard with her, in writing

A refit delivers two things: the yacht, and the file that explains what was done to her. The second is the one nobody puts a price on, and nobody reads until it is the only thing left.

An owner checks the paint under a light before signing. Almost nobody opens the folder. The folder outlasts the crew who took delivery, the captain who ran the project, and often the owner too. The engineer who opens a compartment in six years was not at the redelivery, and works from what is written. There is nothing else.

The file is written while she is open, or not at all

A handover pack cannot be assembled at the gate. Most of what belongs in it can only be recorded while she is still open.

A panel comes off once. The bundle behind it is visible for a week, the weld for the days between fit-up and fairing. After that the information is not mislaid, it is gone. A yard that starts the file in the last fortnight is reconstructing a record from memory, and the memory belongs to people already on the next hull. What comes out of that looks like a handover pack and answers none of the questions one exists to answer.

As-built, not as-drawn

The drawing set is the part most often handed over wrong. What gets issued is the design intent, not the installation.

On an older hull the original drawings may be forty years old, and they were already wrong before this refit began. Every yard she has visited since has added a variation nobody wrote down: a run moved to clear a frame, a valve relocated for access, a penetration made twice. A drawing is as-built only if a draughtsman walked the run after it was finished and redrew what is physically there, deviations included. That walk costs a person and a morning.

What we issue is every system redrawn to what is aboard rather than to what was once intended, on paper and as files, because paper survives a laptop and files survive a locker. An electrician on a future job who trusts an as-drawn loom diagram cuts into the wrong bundle, and the yacht loses days while somebody traces by hand what should have been on a sheet. The specification the job was priced from is the document at the front of it. The as-built set is the same discipline applied at the back.

The work record, indexed by compartment and by date

Five thousand photographs with no index is not a record. It is an archive, and nobody will open it.

Questions arrive in two forms, both ordinary: what is behind this panel, and when was this last touched. The index has to be built while the work runs, because the photographs worth having are of things about to be hidden, and nobody goes back for those. Our own rule is that nothing is covered unseen: structure, systems and wiring are photographed before a panel goes back on, and the photographs go into the owner's file.

The record also has to carry what was not in the scope. One yacht came in for a month's work and went back in the water with two repairs nobody had quoted for: osmosis along the keel line, found once she was out and dry, and rot in the backing pads under her bilge pumps, found when the affected laminate was opened up. Both were reported and put right. That entry is worth more in a file than the contracted work. Unscoped findings exist only where somebody wrote them down.

Two CAT Marine Power generator sets in a white machinery space, standing on resilient feet on chequer-plate flooring; the nearer enclosure carries a Caterpillar control panel reading engine coolant temperature, a printed maintenance schedule taped to the door, hazard decals and a notice reading battery switch is inside.
Two generator sets as installed, each carrying a maker's plate, a control panel and a printed service schedule on the enclosure door. Half a handover pack is already aboard, on labels like these. The work is transcribing them while they are still legible and indexing them to the compartment they sit in.

Certificates, and the numbers a later reading gets compared to

Two kinds of document end up in the same folder. One proves compliance. The other sets a baseline, and it is the one that gets forgotten.

Class certificates, material certificates and test results are familiar enough that they usually arrive. The second group is a set of numbers whose only value is comparison. Two readings taken the same way establish a rate; one of them establishes nothing but a condition. The method, the instrument, the location and the conditions belong beside the figure, or the next reading cannot be set against it.

The person who benefits was not here. The surveyor at the next renewal reads the file and the vessel, in that order. We do not decide what her class or her flag will accept, and nothing here settles what any particular vessel must satisfy. What a class survey asks of the yard is a separate question from what the yard hands over.

Manuals, part numbers, and a list somebody has to order from

A spares list that names equipment but not part numbers is a shopping list. An engineer in a foreign marina at the wrong end of a season cannot buy from it.

Everything fitted in a refit is something somebody will reorder, and the cheapest moment to write the number down is the moment it comes out of its box. A year later the label has faded and the supplier has superseded the line.

Ours is ordinary enough to list. What leaves the yard at redelivery is the as-built set on paper and as files, the photographic record with the certificates and test results indexed to it, the manuals, the spares list with the numbers on it, two days aboard with her engineer and her captain, and a written year on the workmanship. Eleven trades sit on one payroll, and who employs the welder decides whether there is a gap in the file where a subcontractor's paperwork should have been.

The two days are worth what somebody writes down during them, and the questions a crew asks in that time are a map of what the file does not yet explain.

What the pack is worth six years later

Three moments test the pack, and none of them happens at redelivery.

A buyer's surveyor prices what cannot be verified as risk. A file that can be read removes the guess, and nothing else in the transaction does. An adjuster after a loss asks what her condition was before the event, and the answer is either in the file or it is an argument. The same file does the same work when a warranty claim is argued from another marina. The next yard, in another country, reads it to decide where to open.

None of that makes her worth more by itself. It removes the discount applied to an unproven history, which is a different thing and easier to see.

The foreman who ran the refit stays the contact, so there is a person to call rather than a queue, for as long as he is reachable. The file has to be legible to somebody who is not, and writing it for that reader rather than for the owner on the quay is the whole of the discipline.

Written at the yard in Tuzla. What a particular vessel's flag or class will accept of a record is theirs to decide, not ours to state.

Send the drawings you already hold

Send the drawing set you were given, the survey reports and test results from her last two yard periods, the manuals you actually have rather than the ones you should have, and any photographs taken while she was open. Tell us when she is next due out of the water. What comes back is where the record you hold has gaps, and which of them we would have to close on the yacht herself. Write to info@revivarefit.com.