What yacht refitting actually involves, in order

Why the number that moves a refit budget is almost never the work that was quoted, and almost always the work that was found.

What a scoping survey has to establish

A refit begins as a document, not as a job. The document is a condition survey, and its quality decides everything that follows. A yard quoting yacht refitting work from a walk-through and an owner's wish list is quoting a guess, and the guess is always low.

Owners use yacht renovation and refit to mean the same thing. A yard cannot. One is a specification that can be written in advance, and the other is a condition that nobody knows until the panelling is out.

A survey worth the name is dense and located. Ultrasonic thickness readings taken by station and frame. Coating adhesion tested by pull-off rather than assumed from appearance. Tank entry once the tanks are gas-freed. Machinery hours read against the service record and the oil analysis, not against what the last yard wrote in the file.

Density has a limit worth stating. Readings taken at accessible points say nothing about the frames that were never accessible, and those are the frames where water stands. Nothing seen through bonded panelling, behind a tank top, or under a sole that has been down for fifteen years is in the quotation.

One scoping input is not condition at all. A vessel going to charter, a vessel going to long-range cruising and a vessel going to sale are three specifications wearing one word. Deciding late is what turns that difference into variations.

This phase costs money before anything visible has been achieved. It is still the cheapest part of the programme.

Strip-down, and what it finds

Strip-down is quick. Two or three weeks takes a vessel from furnished to bare, and it is the point at which a budget stops being a document and becomes a fact.

What appears is rarely a surprise in kind. It is a surprise in quantity. Wastage under a bilge that never drained properly, or a bilge painted rather than repaired. Fairing compound laid eight millimetres thick over a plating deformation somebody chose not to correct. Cable runs that do not match the as-built drawings, because three previous yards each added one and none amended the diagram.

An honest yacht refurbishment quotation is therefore two numbers. One is priced from the survey. The other is a provision against what the survey could not reach, and that is the number which moves.

Aft deck joinery and deck finishes after refit
The interior closes last, because it is the layer that comes out again when something behind it is found.

Where the trades collide

The sequence is not a preference. Hot work distorts, grinds and contaminates, so structural repairs are closed out before a system is re-run and before a fairing programme starts over the plate. Most of yacht refitting is the management of that overlap.

The collisions are predictable and they are still the thing that goes wrong. A plate renewal under a saloon sole means hot work inside a compartment the interior programme wants closed and protected. A tank recoating means staging, forced ventilation and an exclusion zone that stops other trades within a radius of it. New cable routes cross bulkheads that have already been faired. Each reopening is a second protection, a second clean and a second handover.

Timing decides what a collision costs. Class attends the significant findings, and Class works to its own calendar. A structural finding raised in week two and the same finding raised in week nine cost the same in steel and very different amounts in schedule.

Four or five trades can run at once if there is covered space and workshop capacity to keep them apart. Run them one after another and they do not add a week. They add a quarter.

Why the interior closes last

Joinery is the most visible part of any superyacht refurbishment and the easiest to sell. It is also the layer that comes out again when a hydraulic union weeps behind it or a chilled water line is found to be undersized. A veneer removed to reach a valve is a veneer that will not match on the second attempt.

A yacht interior refit also absorbs the systems decisions taken above it. Modern air handling, larger cable trays and new tankage rarely fit the voids the original equipment left behind, so the joinery drawing changes after the systems drawing does and never before.

Lead times are the other half. Hide, fabric, stone slabs and specialist glass run to twelve or sixteen weeks and do not compress. The decision that protects a delivery date is taken in month one, when the interior specification is frozen and ordered, not in month six when the space is finally ready to receive it. A superyacht refurbishment that is running late usually shows it in the interior, because the interior is where lateness collects.

A refit does not run late in month eight. It runs late in week three.

What refit project management is

Refit project management is not coordination in the diary sense. It is the discipline of pricing and recording a change at the moment it is discovered, and of holding one person answerable for the whole vessel rather than for a department. We would rather issue an uncomfortable number in week three than a reconciliation in month eight.

The owner is a schedule input too, and that part is rarely written into a contract. Ask who signs a variation, and how many days an owner has to answer one, because an unanswered variation stops a trade at the same rate as a missing part.

None of this makes a discovery cheaper. It makes the discovery arrive as a decision rather than as an argument.

  • One manager for the whole vessel. Not a manager for each department, because the seams between trades are where weeks are lost and no department owns a seam.
  • A change order raised at discovery, priced and signed before the trade proceeds, so that nothing in the month-eight invoice is being read by an owner for the first time.
  • Purchasing, customs and freight held by the yard, because an import delay does not announce itself until the trade it feeds is standing still.
  • A weekly report with photographs, dated and cumulative, so progress can be checked against the schedule rather than described over the telephone.

Sea trials and the list after them

Sea trials are not a formality and they are not a celebration. They are the first time the work is loaded. Shaft alignment under load, vibration signature, noise levels in the guest spaces, air conditioning against a real heat load, stabilisers at speed. Findings at this stage are expensive, because the vessel is afloat and most of the trades have demobilised.

A refit does not end at handover either. It ends when the punch list is closed, and a punch list is always longer than a yard would like to present. A short list at handover is usually a list somebody has edited.

There is a version of this business in which the quotation is optimistic, the discovery is absorbed quietly, and the conversation happens in month eight. The alternative reads worse on the day the prices are compared. If a refit is being weighed up, ask to see a variation register and a weekly report from a vessel that has already left the yard. Neither can be written for the asking, and between them they predict the final invoice better than any quotation does. Written at the yard in Tuzla. Figures quoted are the ones we record on the job and hand over with the vessel.