What is a typical Refit Specification?

What is a typical Refit Specification?

The best refit specification document is the longest with the attachments.

The Shipyard

Refit Specification

  • Fresh water tanks cleaning
  • Black water tanks cleaning
  • Grey water tanks cleaning
  • Safety Equipment (LSA) Annual Service
  • Main Engines Port and Starboard 2 sets
    • a) to perform sea trials 2 times: before and after refit period and record main parameters with the step by 100 RPM up to full load:
    • b) to test and record all alarms and safety devices
    • c) cut off test for fuel injectors
    • d) Reports in English after every attendance as per a) b) and c) to be presented to the owner representative for the acceptance
    • e) Coolant and oil samples to send for analysis prior maintenance
  • Diesel Generators Port and Starboard 2 sets
    • a) to perform sea / berth trials 2 times: before and after refit period and record main parameters
    • b) to test and record all alarms and safety devices
    • c) cut off test for fuel injectors
    • d) Reports in English after every attendance as per a) b) and c) to be presented to the owner representative for the acceptance
    • e) Coolant and oil samples to send for analysis prior maintenance
  • Air condition system Chemical cleaning of condensers.
  • Air condition system – professional cleaning and disinfectation of AC fan coils and FAMU
  • Galley
    • Oven and grill with relevant air extracting ducts (total length app 3 meters) professional cleaning
  • Laundry
    • Professional cleaning of air extracting ducts of drying machines and laundry itself.
  • Technical Equipment Annual Service:
    • Watermaker Unit
    • Fresh Water Pumps / Hydrophore Pumps
    • Bilge Pumps
    • Fire Pumps
    • Sprinkler System Annual Service and Maintenance

Shipyard Services

  • Wet berth / Daily rate in the water (to be charged at final balance)
  • Fresh Water  single rate for connection / disconnection (to be charged at final balance)
  • Fresh Water  consumption (to be charged at final balance)
  • Electricity  single rate for connection / disconnection  (to be charged at final balance)
  • Electricity  consumption (to be charged in final balance)
  • Garbage daily rate  (to be charged at final balance)
  • Crane service  (to be charged at final balance)
  • Fork Lift service  (to be charged at final balance)
  • Internal Protection Safety document
  • External Protection: 
  • Diver assistance 
  • Insurance Fee
  • Black water / Grey water disposal (to be charged at final balance)
  • Oily water disposal (to be charged at final balance)
  • Shore Main Fine line under pressure 24/7 (to be charged at final balance)